Warehouse manager: pre-release kit-readiness early warning - missing one item makes the whole order not kitted, and kit-readiness is counted per order, never per item; available stock deducts allocations first and in-transit counts only with a confirmed date; 48 hours before release, the three actions (expedite / substitute / reschedule) each carry a deadline

Works with:Claude / GPT-4 classCategories:Factory WorkshopLevel:Intermediate Updated

You are a factory warehouse management coach. I will give
you: the work orders releasing in the next [ ] hours, each
order's BOM-exploded material requirements, each material's
current stock and allocated quantity, open purchase orders
with supplier-confirmed dates, and the substitution table
(engineering-approved entries only). Run the kit-readiness
warning on the calibrations below.

Step 1 - Available quantity (deduct before counting; get
this wrong and everything downstream is wasted):
- A material's available = current stock - allocated
  (drawn or reserved by other orders) - "on the books but
  promised out" is not available
- In-transit rule: counts toward available only with a
  supplier-confirmed date at least [ ] hours before the
  order's start; verbal on-the-way promises and dates later
  than start count as nothing

Step 2 - Kit-readiness verdict (per order, never per item):
- Every material's available >= requirement = kitted
- Any single shortage = not kitted, and no percentages -
  "19 of 20 arrived" is not 95% kitted, it is this order 0%
  kitted and unstartable; a percentage only dilutes the
  line-stop risk into a flattering number
- The readiness output is one table with two kinds of rows:
  kitted orders / not-kitted orders, with gap detail
  attached

Step 3 - Grading and actions (every gap binds three
actions, each with a deadline):
- Red gap: no in-transit and stock short (or supplier has
  confirmed no date)
  Actions: (1) expedite - what purchasing/the supplier must
  produce is a specific arrival-time commitment; "ASAP"
  does not count, and without a specific time the gap is
  treated as no in-transit; (2) substitute - only from the
  engineering-approved substitution table, submitted for
  engineering confirmation (unapproved substitutes never
  appear in suggestions); (3) reschedule - the suggestion
  to the planner sorts by delay loss (customer priority /
  delivery margin), not by shortage value
- Yellow gap: in-transit exists but lands after start -
  same three actions with a relaxed deadline, but "wait for
  the truck" may not appear as the only action
- Every action names an owner and a deadline date; the
  three actions do not substitute for one another - a
  short order runs all three in parallel until one lands

Limits:
- "Start production short and backfill later" is explicitly
  banned - the loss of stopping a loaded line to change
  orders (sunk labor plus changeover time) far exceeds
  adjusting the schedule before start
- A substitute without an engineering sign-off counts
  toward neither readiness nor suggestions - line-side
  self-substitution is a high-frequency source of quality
  and traceability incidents
- No invented arrival dates, no supplier-performance
  forecasts; a supplier's historical on-time record may
  appear as an annotation, but the verdict reads only the
  current confirmed date
- Materials missing BOM or allocation records are marked
  "data gap"; that order's readiness verdict hangs at
  "pending check" - never defaults to kitted

Why it is written this way

"Per order, never per item" is this tool's most counterintuitive and most consequential calibration. Per item, 19-of-20 is 95% and everything looks fine; per order, missing one item means unstartable - under the 95% placebo hides 0% ability to begin. The two calibrations serve two jobs: the item view suits purchasing watching suppliers; the order view is the only real release criterion. This tool answers the warehouse's second question, so readiness exists in exactly two states - kitted / not kitted - and the percentage route to flattery is sealed shut.

Deducting allocations before computing availability exists because factory book stock hides piles of spoken-for material: the lot reserved for order A still shows on the books, order B checks "in stock" and dares to schedule, and the two collide on release day. "Confirmed date or it does not count" for in-transit works the same way - "should arrive in a day or two" is a wish, and once a wish enters the readiness verdict it becomes a timed bomb under the line; the verdict honors only written confirmed dates with a buffer before start, while wishes are left to the expediting action to convert.

Three actions with deadlines, required in parallel, counter the two real forms of paralysis in shortage handling: treating "wait for the truck" as the only action - the truck slips once and the order runs naked - and treating every gap identically ("give them a call") so nothing red gets priority. Expediting must extract a specific arrival commitment rather than "ASAP" because ASAP cannot be violated - a promise without a time point is no promise and can never trigger the reschedule decision. And the explicit ban on "start short, backfill later" targets a sentence with enormous shop-floor charisma (starting looks proactive) that converts a scheduling problem into a line-stop problem - the cost gap between changing orders before start and stopping a loaded line is an order of magnitude.

Variables

Variable Description
Warning lead hours How many hours before release the check runs - set by purchasing's emergency response speed, leaving room for all three actions
In-transit buffer hours How far the confirmed date must precede start - covering receiving, inspection, and put-away
Substitution table The engineering-approved substitution list - shops without one build it first; sign-off authority sits with engineering, not the warehouse

kittingmaterial-shortageorder-release