Quality control inspector: concession acceptance (deviation) SOP - defect class sets approval authority and customer-notification duty; concession lots carry separate identification traceable to work orders; second same-defect concession with a supplier triggers a corrective meeting, the third freezes their channel; the concession form must precede material issue, always
You are a quality-system process designer at a factory. Turn
the SOP below into an archival, executable standard document -
keep every calibration, complete the forms and role details,
and output printable Markdown.
Scope: incoming or in-process lots judged nonconforming but
assessed as usable under concession. Lots that can be reworked
to spec go through the rework channel, not this SOP.
Gate 1 - Classification (before everything else):
- Class 1, cosmetic: no effect on function, safety, or
regulatory compliance
Approval: QC supervisor, single signature
Customer notice: per contract (where the contract is
silent, default to no proactive notice, but log it)
- Class 2, functional excursion: affects function but
assessed usable for the current application by engineering
Approval: QC + engineering/process, dual signature
Customer notice: mandatory, in writing, and release waits
for the customer's written reply - half of a class-2
release authority belongs to the customer; "acknowledged /
accepted" closes the loop
- Class 3, safety or regulatory: concession prohibited. No
approval channel, no exception clause - only return and
supplier correction
The classification table [filled per your products, see
Variables] attaches to the SOP; new defect types are
classified before any process step runs.
Gate 2 - Sequence (form before material):
- The concession request must exist before the lot is issued
- a request filed after issue is rejected by system and
paper alike and handled as "released without inspection"
- "Production needs it now" is not grounds to skip
assessment: urgency is a scheduling problem, and the first
time quality pays for it, the channel never closes again;
for genuinely urgent lots the assessment deadline may
compress, but no assessment step may be dropped
Gate 3 - Identification and traceability (concession is not
disappearance):
- Concession lots carry a separate lot number/tag, physically
distinguishable from accepted lots
- Flow logged to work orders: which orders drew the
concession lot, which finished-goods lots resulted -
linked to finished-goods and shipment records so the
blast radius can be drawn if the defect recurs
- A concession is valid for this lot only: the supplier's
next lot with the same defect inherits nothing and is
assessed anew
Gate 4 - Look-back (prevent routine-ization):
- Ledger fields: date / supplier / material / defect /
class / quantity / approver / customer reply / work orders
- Weekly concession rate by supplier (concession lots /
total lots received from that supplier)
- Escalation: second concession, same supplier, same defect
-> corrective meeting with the supplier (ledger history
and defect evidence on the table); third -> freeze that
supplier's concession channel for that material; return
and correction are the only paths left
- Concession rate rising [ ] consecutive weeks -> the
problem is reclassified as supplier-management failure,
handed to purchasing - no longer digested inside the
concession process
Prohibitions:
- Back-dated forms: any shape of "use first, paperwork after"
- Lot-splitting to dodge classification: one nonconforming
lot split into small lots to apply at a lower class is
classified as the original lot
- Concession tags removed or covered in downstream
operations - identification survives until finished goods
leave the plant
- Closing a corrective meeting with "we'll be careful next
time" - correction requires written corrective action and
a verification method
Document structure: purpose, scope, classification and
authority, sequence rules, identification and traceability,
ledger and escalation, prohibitions, plus "concession request
form" and "concession ledger" templates.
Why it is written this way
The four gates are ordered deliberately: classification comes before everything because class determines all downstream behavior - between class 1 and class 3 what changes is not strictness but three separate things: who holds authority, whether the customer must be told, and whether a channel exists at all. For class 2, "release only after the customer's written reply" is the link most easily crushed by commercial pressure: with the customer's "accepted," the concession is a jointly acknowledged business decision; without the customer knowing, the same release is unilateral concealment - and when the customer eventually finds out, a technical issue becomes a trust issue of a different order. Class 3 has no channel rather than a senior-approval channel because releasing a safety/regulatory item is irreversible - a signature cannot sign responsibility out of existence.
The "form before material" discipline looks bureaucratic and is in fact the cheapest anti-gaming gate in the whole system. Tolerate one back-dated form and every concession becomes back-dated - use first, assess never. Hooking it to "released without inspection" gives the violation an existing consequence framework instead of depending on someone choosing to care each time. Likewise, "urgency is not grounds to skip assessment" acknowledges urgency as real but reroutes it into compressing the deadline rather than deleting steps - scheduling problems get solved with scheduling, a boundary this SOP keeps returning to.
The look-back gate is the document's actual destination. Any single concession looks reasonable: the customer waits, the line waits, the assessment was done. It becomes a disaster in exactly one way - quiet routine-ization; a supplier you concession every month has a problem that stopped being about this lot long ago. The escalation counts "same supplier, same defect" rather than total concession rate, because totals dilute one supplier's pattern into plant-wide background noise; freezing the channel on the third occurrence turns "supplier management is failing" from a grumble into an automatic mechanical action.
Variables
| Variable | Description |
|---|---|
| Defect classification table | Your products' defect types mapped to class 1/2/3 - an SOP attachment, updated with the product line |
| Customer notification clause | The contract clause covering concessions/deviations - confirm at signing, not at first concession |
| Rate-rise warning weeks | Consecutive rising weeks before reclassifying as supplier-management failure - by receipt frequency; low-frequency shops use months |