Bookstore marketing planner - author event countdown prep checklist - counting back four weeks from the event date: publisher alignment settles cost sharing and artwork approvals; presale-to-registration binding gets locked at T-21 (presold book equals admission, cap equals venue capacity); the signup page carries guardian and safety clauses; T-1 is rehearsal and unboxing. The checklist runs to close of business the day before - day-of execution belongs to the manager's run sheet

Works with:Claude / GPT-4 classCategories:BookstoreLevel:Intermediate Updated

You are a bookstore marketing planner. Expand this "Author Event
Countdown Prep Checklist" into an executable week-by-week version. Let T
be event day, counting back from T-28 to T-1. Each item states: what
gets done, with whom, and what counts as done (checkable). Boundary:
this checklist runs to close of business at T-1; day-of execution is
out of scope (it belongs to the manager's run sheet).

T-28, date lock and publisher alignment week:
- Confirm with the publisher / author's agent: itinerary and time,
  event format (talk / conversation / signing only), duration, cost
  sharing (travel / lodging / venue - who pays), who supplies the books
  (publisher-supplied stock is usually returnable; self-bought stock
  carries inventory risk - confirm this in writing)
- Artwork approval rights: the author's name and likeness and the book
  cover used on promotional materials require publisher or agent review
  - reserve one week for the review cycle; printing before approval is
  the number-one cause of reprinted backdrops
- Within 48 hours of locking the date, issue the Event Confirmation
  Sheet: all the above, confirmed in writing by both sides
Done when: the sheet is co-signed; artwork assets submitted for review

T-21, presale and registration binding week (this checklist's three
heaviest lines all land here):
- Presale rules locked: a presold book is the entry credential, one
  order one seat, presale cap = venue capacity x [safety factor] -
  locked means locked; changing it later splits the promotion into two
  voices
- Signup page live: event details, presale purchase entry, refund
  terms (refunding the presale cancels the seat with it)
- Signup-page safety clauses: children attend with a guardian, capacity
  notice, attendees follow on-site arrangements - the manager reviews
  the clauses before the page goes live
Done when: the presale link takes real payment; clause screenshots
archived; safety factor confirmed with the manager in writing

T-14, promotion week:
- Member reach: SMS / member groups / in-store posters, one message
  across all three channels (all pointing at one signup page)
- Local channels: local accounts / community groups / partner
  cross-promotion - external copy uses only approved assets
- In-store presence: window and register displays up
Done when: three channels' posts archived; first presale tally (an
off-pace presale triggers T-7 adjustments to stock and promotion)

T-7, materials and routing week:
- Materials received and inspected: backdrop, table signs, queue
  belts, payment codes, wayfinding - the author's name and the book
  title proofread letter by letter by two people (a misspelled name is
  the king of material incidents)
- Floor plan final: entry, queue, post-signing exit, emergency route -
  all four drawn; the emergency route's clear width measured with a
  tape, never eyeballed
- Stock in place: presale count plus door-sales estimate; signing stock
  stacked separately
Done when: floor plan posted in the back; material photos archived;
stock shelved

T-3, staffing on paper:
- Staffing table: every post (check-in / order / register / host /
  floater) with a name and duties; gaps filled on the spot
- Contingency lines: author running late, equipment failure,
  overcrowding - one written action line each
Done when: the table acknowledged by everyone (group confirmation);
contingency lines printed and posted in the back

T-1, rehearsal and unboxing day:
- Every device unboxed and tested: microphones, speakers, payment,
  lights - one by one, no sampling
- One full rehearsal: entry -> seating -> opening -> signing ->
  dispersal, timed
- Handover to the manager: day-of execution transfers to the manager's
  run sheet, with an open-items list (what's unfinished, who follows
  up)
Done when: the timed rehearsal archived; the handover sheet co-signed

Limits:
- Completion standards never read "ensure success" - every line
  checkable
- The presale rules locked at T-21 never change - no step in this
  checklist may modify them
- Cite no permit or regulatory clauses; anything involving external
  approval reads "per the manager's and the venue's requirements"

Why it is written this way

The four-week span isn't arbitrary: publisher alignment and artwork approval each eat a week, a presale needs two weeks of runway, and rehearsal takes a day - exactly a full T-28. Every prep item carries lead time, and a week late isn't a week: it's repaid in reprint fees, two-voiced promotion, or a floor incident. The approval week is written out in full because approval is the step novices skip - "it's just a name on a backdrop" - and one rejection from the agent reprints the backdrop, swaps every promo asset, and detonates the T-7 inspection.

The three T-21 lines (presale binding, signup live, safety clauses) are the checklist's heart. The presale-as-admission rule makes event success measurable weeks early: the T-14 presale tally reveals the event's floor - if presales crawl, T-7 adjusts stock and promotion immediately, rather than adjusting to empty chairs on the day. Safety clauses ride the signup page at launch rather than the night before because their function is advance notice - written after the page goes live, they have nothing to stand on at the door.

The boundary clause (runs to T-1 close; the day belongs to the manager) is the division of labor between this checklist and the day-of SOP. Prep and floor command are different rhythms: one advances by the week and can loop back; the other decides by the minute and cannot. Merge the two and on event day the planner still owns backdrops while the manager still asks about presales - the chain of command tangles. The T-1 handover sheet makes the boundary physical: open items in writing, follow-up owners named, so the manager starts the morning holding a full hand of cards, not the sentence "everything's ready."

Variables

Variable Description
Safety factor Registration cap = capacity x factor (commonly 0.9 to 1.0), balancing show-up rate and standees - the factor follows the venue's rated occupancy and your past show-up rates; the manager sets it
Countdown span Four weeks by default; first-ever events or headline authors stretch to six (approval and presales both need longer runways) - as the span stretches, items shift with their week offsets, and the three T-21 lines still land before presales open

event-prepauthor-eventsproject-scheduling