Factory purchasing: supplier on-time delivery analyzer - on-time percentage mixes two completely different bads (rare huge delays that stop lines, versus frequent small delays that grind daily), and its calibrations are all water: the promised date rolls forward with each delay so the rate always looks fine, and 'arrival' gets recorded at ship date so transit time hides; the verdict anchors on two unmovable points, the first confirmed delivery date (a reschedule is an event, not a refresh) and the dock-in date; long-tail suppliers (on-time on average but with rare extra-long delays) get their own table - the kind you can't see coming and can't stock against

Works with Claude / GPT-4 class

Factory WorkshopAdvanced

"Purchasing grades supplier delivery by on-time percentage,...